Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-09-25 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 042 Payment period ending: 08-20-25 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 164,143,237.20 1,517,158.50 2. a. Extra Work 5,436,935.63 1,153,329.84 b. Adustment Comp. -866,754.52 -418,587.63 3. Materials on Hand 347,022.32 -59,670.46 4. Earned Subject to Retention 169,060,440.63 2,192,230.25 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 187,578,418.31 7. Deductions -77,778.55 -50,243.86 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 187,847,662.08 2,141,986.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,141,986.39