Dept. of Trans. PROGRESS Serial No. Contract No. 25-265-08-39 08-1C0814 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 95% Location: Federal Project: 08-RIV-10-R60.7/R74.3 NONE Progress payment No. 043 Payment period ending: 09-20-25 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 165,045,332.20 902,095.00 2. a. Extra Work 6,231,634.65 794,699.02 b. Adustment Comp. -805,308.70 61,445.82 3. Materials on Hand 237,166.58 -109,855.74 4. Earned Subject to Retention 170,708,824.73 1,648,384.10 5. Mobilization 18,865,000.00 0.00 6. Total Work Completed 189,336,658.15 7. Deductions -77,778.55 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 189,496,046.18 1,648,384.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,648,384.10