Dept. of Trans. PROGRESS Serial No. Contract No. 22-089-10-28 08-1C0824 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 17% Location: Federal Project: 08-RIV-10-R104.9/R134.2 B1IM-010-3(112) Progress payment No. 006 Payment period ending: 03-20-22 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,059,341.71 -936,332.70 2. a. Extra Work 26,071,268.00 26,071,268.00 b. Adustment Comp. 3. Materials on Hand 2,700,000.00 2,700,000.00 4. Earned Subject to Retention 32,830,609.71 27,834,935.30 5. Mobilization 20,241,040.88 20,241,040.88 6. Total Work Completed 50,371,650.59 7. Deductions -153,052.95 -153,052.95 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,918,597.64 47,922,923.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,922,923.23