Dept. of Trans. PROGRESS Serial No. Contract No. 23-172-11-00 08-1C0824 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 69% Location: Federal Project: 08-RIV-10-R104.9/R134.2 B1IM-010-3(112) Progress payment No. 021 Payment period ending: 06-20-23 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,645,039.03 16,320,786.40 2. a. Extra Work 40,342,616.96 203,735.00 b. Adustment Comp. 9,975,883.74 84,069.18 3. Materials on Hand 1,628,052.56 -1,896,831.22 4. Earned Subject to Retention 158,591,592.29 14,711,759.36 5. Mobilization 26,988,054.50 0.00 6. Total Work Completed 183,951,594.23 7. Deductions -204,070.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 185,375,576.19 14,711,759.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,711,759.36