Dept. of Trans. PROGRESS Serial No. Contract No. 24-236-11-02 08-1C0824 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 87% Location: Federal Project: 08-RIV-10-R104.9/R134.2 B1IM-010-3(112) Progress payment No. 035 Payment period ending: 08-20-24 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 164,120,139.14 1,985,388.15 2. a. Extra Work 53,689,153.08 386,349.39 b. Adustment Comp. 11,699,981.57 1,421,895.45 3. Materials on Hand 185,923.23 0.00 4. Earned Subject to Retention 229,695,197.02 3,793,632.99 5. Mobilization 26,988,054.50 0.00 6. Total Work Completed 256,497,328.29 7. Deductions -204,070.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 256,479,180.92 3,793,632.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,793,632.99