Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-12-47 08-1C08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 21% Location: Federal Project: 08-RIV-10-R134.0/R156.5 ACNH-105(52) Progress payment No. 012 Payment period ending: 11-20-24 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,986,811.00 1,477,230.00 2. a. Extra Work 14,450,410.25 864,453.50 b. Adustment Comp. 3. Materials on Hand 2,284,583.50 1,314,864.15 4. Earned Subject to Retention 24,721,804.75 3,656,547.65 5. Mobilization 17,695,357.19 0.00 6. Total Work Completed 40,132,578.44 7. Deductions -277,939.76 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 42,139,222.18 3,659,547.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,659,547.65