Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-12-15 08-1C08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 33% Location: Federal Project: 08-RIV-10-R134.0/R156.5 ACNH-105(52) Progress payment No. 019 Payment period ending: 06-20-25 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,120,510.38 4,740,379.08 2. a. Extra Work 18,380,660.30 364,631.83 b. Adustment Comp. 65,915.09 0.00 3. Materials on Hand 631,647.11 -893,652.23 4. Earned Subject to Retention 93,198,732.88 4,211,358.68 5. Mobilization 22,414,119.10 0.00 6. Total Work Completed 114,981,204.87 7. Deductions -396,357.03 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 115,216,494.95 4,216,358.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,216,358.68