Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-13-15 08-1C08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 37% Location: Federal Project: 08-RIV-10-R134.0/R156.5 ACNH-105(52) Progress payment No. 020 Payment period ending: 07-20-25 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,629,766.88 3,509,256.50 2. a. Extra Work 20,045,593.85 1,664,933.55 b. Adustment Comp. 65,915.09 0.00 3. Materials on Hand 307,005.06 -324,642.05 4. Earned Subject to Retention 98,048,280.88 4,849,548.00 5. Mobilization 22,414,119.10 0.00 6. Total Work Completed 120,155,394.92 7. Deductions -368,057.03 28,300.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 120,094,342.95 4,877,848.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,877,848.00