Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-12-19 08-1C08U4 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 39% Location: Federal Project: 08-RIV-10-R134.0/R156.5 ACNH-105(52) Progress payment No. 021 Payment period ending: 08-20-25 FISHER SAND & GRAVEL CO 1302 W. DRIVERS WAY TEMPE AZ 85284 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 81,925,309.38 4,295,542.50 2. a. Extra Work 22,015,840.89 1,970,247.04 b. Adustment Comp. 65,915.09 0.00 3. Materials on Hand 307,005.06 0.00 4. Earned Subject to Retention 104,314,070.42 6,265,789.54 5. Mobilization 22,414,119.10 0.00 6. Total Work Completed 126,421,184.46 7. Deductions -373,057.03 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 126,355,132.49 6,260,789.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,260,789.54