Dept. of Trans. PROGRESS Serial No. Contract No. 16-300-16-20 08-1C0914 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 53% Location: Federal Project: 08-RIV-60-R12.2/22.1 NHP-P060(147) Progress payment No. 004 Payment period ending: 10-20-16 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,303,796.00 2,966,195.20 2. a. Extra Work 2,887.94 0.00 b. Adustment Comp. 354,831.49 93,945.52 3. Materials on Hand 66,922.75 -38,485.25 4. Earned Subject to Retention 10,728,438.18 3,021,655.47 5. Mobilization 356,000.00 17,800.00 6. Total Work Completed 11,017,515.43 7. Deductions -36,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,048,438.18 3,029,455.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,029,455.47