Dept. of Trans. PROGRESS Serial No. Contract No. 17-172-16-16 08-1C0914 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 67% Location: Federal Project: 08-RIV-60-R12.2/22.1 NHP-P060(147) Progress payment No. 012 Payment period ending: 06-20-17 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,927,949.14 1,512,393.60 2. a. Extra Work 29,879.56 0.00 b. Adustment Comp. 456,521.68 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,414,350.38 1,512,393.60 5. Mobilization 356,000.00 0.00 6. Total Work Completed 14,770,350.38 7. Deductions -13,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,757,350.38 1,512,393.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,512,393.60