Dept. of Trans. PROGRESS Serial No. Contract No. 17-235-13-30 08-1C0914 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 87% Location: Federal Project: 08-RIV-60-R12.2/22.1 NHP-P060(147) Progress payment No. 014 Payment period ending: 08-18-17 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,668,050.47 424,910.68 2. a. Extra Work 185,694.24 0.00 b. Adustment Comp. 665,143.28 6,490.69 3. Materials on Hand 4. Earned Subject to Retention 17,518,887.99 431,401.37 5. Mobilization 356,000.00 0.00 6. Total Work Completed 17,874,887.99 7. Deductions -136,850.34 -113,850.34 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,738,037.65 317,551.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 317,551.03