Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-16-26 08-1C0914 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 97% Location: Federal Project: 08-RIV-60-R12.2/22.1 NHP-P060(147) Progress payment No. 015 Payment period ending: 09-20-17 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,896,351.46 228,300.99 2. a. Extra Work 246,872.17 61,177.93 b. Adustment Comp. 660,337.49 -4,805.79 3. Materials on Hand 4. Earned Subject to Retention 17,803,561.12 284,673.13 5. Mobilization 356,000.00 0.00 6. Total Work Completed 18,159,561.12 7. Deductions -29,000.00 107,850.34 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,130,561.12 392,523.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 392,523.47