Dept. of Trans. PROGRESS Serial No. Contract No. 18-204-09-26 08-1C1004 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 98% Location: Federal Project: 08-RIV-18-9.1/17.8 ACNH-P018(58) Progress payment No. 002 Payment period ending: 07-20-18 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 630,800.50 580,993.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 386,466.00 -132,950.00 4. Earned Subject to Retention 1,017,266.50 448,043.00 5. Mobilization 152,500.00 0.00 6. Total Work Completed 783,300.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -44,804.30 -44,804.30 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,124,962.20 403,238.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 403,238.70