Dept. of Trans. PROGRESS Serial No. Contract No. 18-236-11-21 08-1C1004 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 17% Location: Federal Project: 08-RIV-18-9.1/17.8 ACNH-P018(58) Progress payment No. 003 Payment period ending: 08-20-18 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,590,665.64 1,959,865.14 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 320,689.00 -65,777.00 4. Earned Subject to Retention 2,911,354.64 1,894,088.14 5. Mobilization 289,750.00 137,250.00 6. Total Work Completed 2,880,415.64 7. Deductions -28,506.93 -28,506.93 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 44,804.30 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,172,597.71 2,047,635.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,047,635.51