Dept. of Trans. PROGRESS Serial No. Contract No. 18-268-07-31 08-1C1004 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 96% Location: Federal Project: 08-RIV-18-9.1/17.8 ACNH-P018(58) Progress payment No. 004 Payment period ending: 09-20-18 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,245,018.64 3,654,353.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 310,120.00 -10,569.00 4. Earned Subject to Retention 6,555,138.64 3,643,784.00 5. Mobilization 305,000.00 15,250.00 6. Total Work Completed 6,550,018.64 7. Deductions -28,506.93 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -364,378.40 -364,378.40 c. Reduction after 95% Comp. 9. Total pay to Contractor 6,467,253.31 3,294,655.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,294,655.60