Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-311-07-38 08-1C1404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-15-4.8/6.4 ACIM-015-5(161) Progress payment No. 006 Payment period ending: 10-11-17 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 684,591.01 0.00 2. a. Extra Work 13,366.87 1,781.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 697,957.88 1,781.52 5. Mobilization 81,358.98 0.00 6. Total Work Completed 779,316.86 7. Deductions 0.00 660.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 779,316.86 2,441.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,441.52