Dept. of Trans. PROGRESS Serial No. Contract No. 19-022-12-22 08-1C1604 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 54% Location: Federal Project: 08-RIV-60-12.1/21.5 ACNH-X065(113) 08-RIV-215-R38.3/38.9 Progress payment No. 003 Payment period ending: 01-20-19 ARAMEXX GROUP INC DBA ARAMEXX CONSTRUCTION 532 W FIRST ST UNIT 202 CLAREMONT CA 91711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 350,525.00 202,816.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 350,525.00 202,816.00 5. Mobilization 94,952.50 19,990.00 6. Total Work Completed 445,477.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 445,477.50 222,806.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,806.00