Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-16-28 08-1C1804 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 69% Location: Federal Project: 08-SBD-60-0.0/1.8 ACNH-P060(150) Progress payment No. 002 Payment period ending: 09-20-17 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 235,258.00 207,148.00 2. a. Extra Work 2,293.15 2,293.15 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 237,551.15 209,441.15 5. Mobilization 52,250.00 24,750.00 6. Total Work Completed 289,801.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 289,801.15 234,191.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 234,191.15