Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-15-08 08-1C29U4 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 25% Location: Federal Project: 08-SBD-10-26.8/34.2 ACIM-010-2(270) Progress payment No. 004 Payment period ending: 02-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 986,387.32 404,454.32 2. a. Extra Work 25,384.13 7,032.48 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,011,771.45 411,486.80 5. Mobilization 423,057.13 89,064.66 6. Total Work Completed 1,434,828.58 7. Deductions -5,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,429,828.58 502,551.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 502,551.46