Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-11-04 08-1C3404 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 97% Location: Federal Project: 08-RIV-74-27.5/32.3 NONE Progress payment No. 004 Payment period ending: 09-16-16 VSS INTERNATIONAL INC 3785 CHANNEL DRIVE WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 758,154.56 68,796.13 2. a. Extra Work 20,110.09 20,110.09 b. Adustment Comp. 20,564.39 20,564.39 3. Materials on Hand 4. Earned Subject to Retention 798,829.04 109,470.61 5. Mobilization 9,000.00 0.00 6. Total Work Completed 807,829.04 7. Deductions -57,000.00 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 750,829.04 59,470.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,470.61