Dept. of Trans. PROGRESS Serial No. Contract No. 20-297-11-06 08-1C38U4 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 24% Location: Federal Project: 08-RIV-10-6.7/R25.1 ACIM-010-3(110) Progress payment No. 010 Payment period ending: 10-20-20 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,681,081.92 3,039,984.98 2. a. Extra Work 9,113,226.80 162,754.41 b. Adustment Comp. 792,802.53 0.00 3. Materials on Hand 889,311.15 196,856.92 4. Earned Subject to Retention 29,476,422.40 3,399,596.31 5. Mobilization 13,639,125.00 0.00 6. Total Work Completed 42,226,236.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,115,547.40 3,399,596.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,399,596.31