Dept. of Trans. PROGRESS Serial No. Contract No. 21-027-09-28 08-1C38U4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 32% Location: Federal Project: 08-RIV-10-6.7/R25.1 ACIM-010-3(110) Progress payment No. 013 Payment period ending: 01-20-21 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,908,625.97 3,487,371.11 2. a. Extra Work 10,688,981.13 211,445.02 b. Adustment Comp. 817,869.33 19,433.25 3. Materials on Hand 175,557.06 -122,596.67 4. Earned Subject to Retention 44,591,033.49 3,595,652.71 5. Mobilization 17,276,225.00 0.00 6. Total Work Completed 61,691,701.43 7. Deductions -167,088.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 61,700,170.49 3,595,652.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,595,652.71