Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-15-04 08-1C38U4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 94% Location: Federal Project: 08-RIV-10-6.7/R25.1 ACIM-010-3(110) Progress payment No. 040 Payment period ending: 12-20-22 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,423,739.74 1,754,309.39 2. a. Extra Work 22,813,228.97 133,560.81 b. Adustment Comp. 3,005,014.25 459,690.42 3. Materials on Hand 837,062.69 -344,818.29 4. Earned Subject to Retention 156,079,045.65 2,002,742.33 5. Mobilization 18,185,500.00 0.00 6. Total Work Completed 173,427,482.96 7. Deductions -550,864.55 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 173,713,681.10 2,002,742.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,002,742.33