Dept. of Trans. PROGRESS Serial No. Contract No. 13-238-16-00 08-1C4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 29% 08-RIV-74-63.0/67.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-13 GRANITE CONSTRUCTION COMPANY 38000 MONROE STREET INDIO, CA 92203 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 730,077.60 730,077.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 730,077.60 730,077.60 5. Mobilization 161,500.00 161,500.00 6. Total Work Completed 891,577.60 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 887,577.60 887,577.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 887,577.60