Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-16-29 08-1C5104 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 52% Location: Federal Project: 08-RIV-74-17.8 NONE Progress payment No. 003 Payment period ending: 09-15-17 HAL HAYS CONSTRUCTION INC 4181 LATHAM ST RIVERSIDE CA 92501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 389,411.85 117,710.89 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 389,411.85 117,710.89 5. Mobilization 6. Total Work Completed 389,411.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 389,411.85 117,710.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,710.89