Dept. of Trans. PROGRESS Serial No. Contract No. 17-144-16-08 08-1C6104 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 70% Location: Federal Project: 08-RIV-15-45.6/47.3 NONE Progress payment No. 002 Payment period ending: 05-20-17 PACIFIC RESTORATION GROUP INC 325 E. ELLIS AVE PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 76,318.00 56,588.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 76,318.00 56,588.00 5. Mobilization 15,000.00 5,000.00 6. Total Work Completed 91,318.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 91,318.00 61,588.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,588.00