Dept. of Trans. PROGRESS Serial No. Contract No. 18-058-13-00 08-1C6304 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 43% Location: Federal Project: 08-VAR ACST-P000-C(433) Progress payment No. 005 Payment period ending: 02-20-18 HIGHLIGHT ELECTRIC INC 6942 ED PERKIC ST #A RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 546,564.48 382,012.72 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 994,868.00 -5,131.00 4. Earned Subject to Retention 1,541,432.48 376,881.72 5. Mobilization 213,548.00 10,677.40 6. Total Work Completed 760,112.48 7. Deductions -100,139.78 -99,139.78 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,654,840.70 288,419.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 288,419.34