Dept. of Trans. PROGRESS Serial No. Contract No. 18-086-10-35 08-1C6304 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 59% Location: Federal Project: 08-VAR ACST-P000-C(433) Progress payment No. 007 Payment period ending: 03-20-18 HIGHLIGHT ELECTRIC INC 6942 ED PERKIC ST #A RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 787,581.00 241,016.52 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 806,470.39 -188,397.61 4. Earned Subject to Retention 1,594,051.39 52,618.91 5. Mobilization 213,548.00 0.00 6. Total Work Completed 1,001,129.00 7. Deductions -2,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,805,599.39 54,618.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,618.91