Dept. of Trans. PROGRESS Serial No. Contract No. 18-115-14-15 08-1C6304 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 75% Location: Federal Project: 08-VAR ACST-P000-C(433) Progress payment No. 008 Payment period ending: 04-20-18 HIGHLIGHT ELECTRIC INC 6942 ED PERKIC ST #A RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,244,734.40 457,153.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 547,942.41 -258,527.98 4. Earned Subject to Retention 1,792,676.81 198,625.42 5. Mobilization 213,548.00 0.00 6. Total Work Completed 1,458,282.40 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -19,862.54 -19,862.54 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,984,362.27 178,762.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 178,762.88