Dept. of Trans. PROGRESS Serial No. Contract No. 20-266-07-52 08-1C6604 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 36% Location: Federal Project: 08-RIV-215-R9.0/R16.0 ACIM-215-1(250) Progress payment No. 002 Payment period ending: 09-20-20 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 130,402.25 125,402.25 2. a. Extra Work 718.75 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 131,121.00 125,402.25 5. Mobilization 101,250.00 101,250.00 6. Total Work Completed 232,371.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 232,371.00 226,652.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 226,652.25