Dept. of Trans. PROGRESS Serial No. Contract No. 24-165-16-30 08-1C7704 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 70% Location: Federal Project: 08-SBD-15-80.6/118.5 NONE 08-SBD-15-R119.1 Progress payment No. 002 Payment period ending: 06-20-24 RE CHAFFEE CONSTRUCTION INC PO BOX 3087 WRIGHTWOOD CA 92397 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 637,342.40 381,521.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 637,342.40 381,521.00 5. Mobilization 6. Total Work Completed 637,342.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 637,342.40 381,521.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 381,521.00