Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-066-13-00 08-1C8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-215-38.6/38.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-14-13 COFFMAN SPECIALTIES, INC. 9685 VIA EXCELENCIA, STE 200 SAN DIEGO, CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 248,771.51 55,676.29 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 248,771.51 55,676.29 5. Mobilization 6. Total Work Completed 248,771.51 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 248,771.51 55,676.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,676.29