Dept. of Trans. PROGRESS Serial No. Contract No. 15-266-09-10 08-1C9004 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 84% Location: Federal Project: 08-RIV-15-27.7/40.9 BRNH-X065(99) Progress payment No. 005 Payment period ending: 09-16-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 519,648.23 112,466.63 2. a. Extra Work 10,172.67 10,172.67 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 529,820.90 122,639.30 5. Mobilization 65,000.00 0.00 6. Total Work Completed 594,820.90 7. Deductions -84,000.00 -82,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 510,820.90 40,639.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,639.30