Dept. of Trans. PROGRESS Serial No. Contract No. 18-142-12-38 08-1E0504 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 16% Location: Federal Project: 08-RIV-74-R14.9 HSST-GP07-4(64) Progress payment No. 003 Payment period ending: 05-20-18 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 677,075.08 231,394.39 2. a. Extra Work 4,409.57 4,409.57 b. Adustment Comp. 27,633.00 27,633.00 3. Materials on Hand 4. Earned Subject to Retention 709,117.65 263,436.96 5. Mobilization 82,896.15 0.00 6. Total Work Completed 792,013.80 7. Deductions -5,778.19 -5,778.19 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 786,235.61 257,658.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,658.77