Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-16-30 08-1E1004 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 08-RIV-79-R33.9 ACHS-STBG-P(79) Progress payment No. 006 Payment period ending: 08-04-17 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 984,856.16 23,244.40 2. a. Extra Work 30,536.94 2,019.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,015,393.10 25,264.16 5. Mobilization 82,000.00 0.00 6. Total Work Completed 1,097,393.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,097,393.10 25,264.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,264.16