Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-08-59 08-1E1404 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 14% Location: Federal Project: 08-VAR SSTG-S079(48) Progress payment No. 002 Payment period ending: 02-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 773,558.21 476,253.23 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 139,736.00 139,736.00 4. Earned Subject to Retention 913,294.21 615,989.23 5. Mobilization 555,000.00 555,000.00 6. Total Work Completed 1,328,558.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,468,294.21 1,170,989.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,170,989.23