Dept. of Trans. PROGRESS Serial No. Contract No. 25-232-13-52 08-1E1404 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 57% Location: Federal Project: 08-VAR SSTG-S079(48) Progress payment No. 008 Payment period ending: 08-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,336,376.64 594,169.68 2. a. Extra Work 150,264.87 71,213.81 b. Adustment Comp. 3. Materials on Hand 29,709.00 -2,618.00 4. Earned Subject to Retention 5,516,350.51 662,765.49 5. Mobilization 740,000.00 0.00 6. Total Work Completed 6,226,641.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,256,350.51 662,765.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 662,765.49