Dept. of Trans. FINAL Serial No. Contract No. 15-107-09-07 08-1E1504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-15-7.9/8.6 NONE Progress payment No. 003 Payment period ending: 09-22-14 STERNDAHL ENTERPRISES, INC. 11861 BRANFORD STREET SUN VALLEY, CA 91352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,901.50 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 55,901.50 0.00 5. Mobilization 6. Total Work Completed 55,901.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,901.50 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00