Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-056-13-59 08-1E2504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-15-20.2 NONE Progress payment No. 002 Payment period ending: 02-04-15 MGP CONSTRUCTION P.O. BOX 355 UPLAND, CA 91785 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 125,258.00 0.00 2. a. Extra Work 34,367.00 34,367.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 159,625.00 34,367.00 5. Mobilization 6. Total Work Completed 159,625.00 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 158,625.00 33,367.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,367.00