Dept. of Trans. PROGRESS Serial No. Contract No. 14-329-11-07 08-1E2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 98% 08-RIV-86-4.2/5.2 Federal Project: ER Progress payment No. 05 Payment period ending: 11-18-14 GRIFFITH COMPANY 3050 E. BIRCH STREET BREA, CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 680,527.41 274,992.26 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 680,527.41 274,992.26 5. Mobilization 6. Total Work Completed 680,527.41 7. Deductions -5,000.00 -2,000.80 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 675,527.41 272,991.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 272,991.46