Dept. of Trans. PROGRESS Serial No. Contract No. 17-055-10-30 08-1E3004 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 43% Location: Federal Project: 08-RIV-15-33.1/35.8 NONE Progress payment No. 001 Payment period ending: 02-20-17 V A P CONSTRUCTION INC 15705 BIRCHWOOD ST LA MIRADA CA 90638 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 139,930.00 139,930.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 139,930.00 139,930.00 5. Mobilization 6. Total Work Completed 139,930.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 139,930.00 139,930.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,930.00