Dept. of Trans. PROGRESS Serial No. Contract No. 21-055-11-22 08-1E5704 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 100% Location: Federal Project: 08-RIV-10-27.6 NONE Progress payment No. 011 Payment period ending: 02-20-21 ROCKFORCE CONSTRUCTION LLC 26772 VISTA TERRACE LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,863,095.50 609,310.00 2. a. Extra Work 134,198.77 10,380.20 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 5,997,294.27 619,690.20 5. Mobilization 951,096.50 0.00 6. Total Work Completed 6,948,390.77 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 14,500.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 6,936,390.77 634,190.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 634,190.90