Dept. of Trans. PROGRESS Serial No. Contract No. 19-143-15-13 08-1E5814 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 90% Location: Federal Project: 08-SBD-95-40.0/40.4 SSTG-P095(31) Progress payment No. 004 Payment period ending: 05-20-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 858,378.50 127,031.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 858,378.50 127,031.10 5. Mobilization 74,000.50 0.00 6. Total Work Completed 932,379.00 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 928,379.00 123,031.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,031.10