Dept. of Trans. PROGRESS Serial No. Contract No. 19-169-12-13 08-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 68% Location: Federal Project: 08-SBD-62-41.0/41.5 HSST-P062(43) Progress payment No. 004 Payment period ending: 06-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,512,305.50 415,476.31 2. a. Extra Work b. Adustment Comp. -2,387.56 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,509,917.94 415,476.31 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,634,917.94 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,614,917.94 405,476.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 405,476.31