Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-08-40 08-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 79% Location: Federal Project: 08-SBD-62-41.0/41.5 HSST-P062(43) Progress payment No. 005 Payment period ending: 07-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,691,315.24 179,009.74 2. a. Extra Work b. Adustment Comp. -2,387.56 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,688,927.68 179,009.74 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,813,927.68 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,793,927.68 179,009.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,009.74