Dept. of Trans. PROGRESS Serial No. Contract No. 19-235-13-20 08-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 79% Location: Federal Project: 08-SBD-62-41.0/41.5 HSST-P062(43) Progress payment No. 006 Payment period ending: 08-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,691,315.24 0.00 2. a. Extra Work 25,619.37 25,619.37 b. Adustment Comp. -2,387.56 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,714,547.05 25,619.37 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,839,547.05 7. Deductions -40,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,799,547.05 5,619.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,619.37