Dept. of Trans. PROGRESS Serial No. Contract No. 19-262-13-16 08-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 08-SBD-62-41.0/41.5 HSST-P062(43) Progress payment No. 007 Payment period ending: 09-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,691,315.24 0.00 2. a. Extra Work 38,381.64 12,762.27 b. Adustment Comp. -3,058.96 -671.40 3. Materials on Hand 4. Earned Subject to Retention 1,726,637.92 12,090.87 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,851,637.92 7. Deductions -43,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,808,637.92 9,090.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,090.87