Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-162-09-56 08-1E6104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-62-41.0/41.5 HSST-P062(43) Progress payment No. 009 Payment period ending: 10-16-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,692,365.24 0.00 2. a. Extra Work 79,804.01 0.00 b. Adustment Comp. -3,058.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,769,110.29 0.00 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,894,110.29 7. Deductions -3,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,891,110.29 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00