Dept. of Trans. PROGRESS Serial No. Contract No. 17-172-16-19 08-1E6504 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 11% Location: Federal Project: 08-RIV-60-R0.0/12.2 ACHS-NHP0-6(14) Progress payment No. 002 Payment period ending: 06-20-17 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 402,156.13 309,639.38 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 136,664.39 136,664.39 4. Earned Subject to Retention 538,820.52 446,303.77 5. Mobilization 417,500.00 417,500.00 6. Total Work Completed 819,656.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 956,320.52 863,803.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 863,803.77